RG * NEW has many reasons to appeal 2022 DNS/SEPA (article)
RG * NEW submitted an article to the Newport Miner on our reasons for appealing the revised 2022 DNS/SEPA that pertains to the draft Comprehensive Plans, Development Regulations, and the Critical Area Codes. The below
PUD and Cascade Digital Mining sign an agreement for power
PUD 2022_08_12 WSPP Master Confirm_Fully Executed PUD Power Agreement 2022_08_02 ESA_fully executed_one lines removed
Cryptomining electronic waste and other toxic e-waste is a massive problem world wide and now it’s a local problem.
Responsible Growth * NE Washington has never received a satisfactory answer much less an answer to our question to Merkle Standard of how the massive e-waste generated from its 30,000 machines and other electronic waste
Responsible Growth * NE Washington Public Radio Interview questions Merkle Standard Cryptomining
Bitcoin mining facility in Pend Oreille Co. draws questions about power use, zoning
Merkle Standard Cryptomining receives SEPA and CUP go ahead with conditions.
Usk cryptomine gets conditional use permit - The Spokesman-Review
POC Hearing Examiner gives Merkle Standard Cryptomining a thumbs up
Decision CUP-2021-012 Ponderay Industries